The Hanover County Montpelier Recreation Center and Library project has received zoning approvals and is currently under design. The project consists of a roughly 20,000-square-foot building that will house a recreation center with a full-size gymnasium and two classrooms in addition to a new library with a conference space and study rooms. The project also includes a new paved parking lot, construction of a relocated ballfield (Wickham Field), and connecting walkways.
Project Timeline
July – November 2022: Completion of design, site plan approval, and permitting.
November 2022 – March 2023: Procurement for Construction
April 2023 – Mid 2024: Construction
If you have any questions or comments regarding this project, please reach out to us at [email protected].
Information gathered for that meeting was utilized to make any necessary changes to the Conditional Use Permit and Special Exception Permit. A revised sketch plan was then submitted to the Hanover County Planning Department for review at the April 21, 2022, meeting of the Planning Commission.